Boeing to delay 787 Dreamliner up to 10 months, report says

By | November 5, 2010, 1:34 PM PDT

More delays have hit Boeing’s flagship aircraft.

The Chicago, Ill.-based aerospace firm has told several of its early 787 Dreamliner customers to expect delivery delays of up to 10 months, according to an Aviation Week report.

That includes:

  • A 10 month delay for Korean Air, which will receive its first 787 in August 2012.
  • A five month delay for Air India, which will receive its first 787 in September or October 2011.
  • A three month delay for Japan Airlines, which will receive its first 787 in June 2011 “at the earliest.”

Boeing reportedly did not offer comment.

Boeing’s big beauty has been the victim of a number of delays — including its maiden flight — due to supplier and production issues.

Previously on SmartPlanet:

Boeing hasn’t issued a statement about its scheduled delivery of the first 787 to All Nippon Airways in the first quarter 2011, but the Aviation Week report cites sources that say a delay is inevitable.

Why? “Late design changes” and other out-of-sequence work that must be incorporated into new production aircraft as well as the 22 787s that have already been completed, according to the report.

The aircraft is now pushing three years late on its original timeline.

Start your week smarter with our weekly e-mail newsletter. It's your cheat sheet for good ideas. Get it.

Andrew Nusca

About Andrew Nusca

Andrew Nusca is the editor of SmartPlanet.

Andrew Nusca

Andrew Nusca

Editor

Andrew Nusca is editor of SmartPlanet and an associate editor for ZDNet. Previously, he worked at Money, Men's Vogue and Popular Mechanics magazines. He holds degrees from the Columbia University Graduate School of Journalism and New York University. He based in New York but resides in Philadelphia.

Follow him on Twitter.

Andrew Nusca

Andrew Nusca
Andrew Nusca does not hold any investments in the companies he covers.
If you liked this, don't miss...
1
Comments

Join the conversation!

Follow via:
RSS
+1 Vote
+ -
RE: Boeing to delay 787 Dreamliner up to 10 months, report says
And this the company that has the inside track for the new tanker aircraft when Northrop Grumman/EADS won the first go-round of the tanker contract. The NG/EADS had proposed a tanker that was flying and being certified w/US Aircraft. The Boeing proposal? It only existed on paper, had never been flown and has been delayed more than 2 years to their first customer...
Posted by mike.horak@...
8th Nov 2010
Join the conversation
Formatting +
BB Codes - Note: HTML is not supported in forums
  • [b] Bold [/b]
  • [i] Italic [/i]
  • [u] Underline [/u]
  • [s] Strikethrough [/s]
  • [q] "Quote" [/q]
  • [ol][*] 1. Ordered List [/ol]
  • [ul][*] · Unordered List [/ul]
  • [pre] Preformat [/pre]
  • [quote] "Blockquote" [/quote]

Join the SmartPlanet community and join the conversation! Signing up is fast and free. Don't wait -- we want to hear your opinion!